This functionality is only available for certain module packages. Info / Copyright

Dialog Verify project

In this dialog you specify which actions are to be carried out by EPLAN during the project verification. When verifying projects, the settings and properties of a comparison project are compared with those of an incoming project. Likewise, targeted check runs are carried out on the incoming project.

The following dialog elements are available:

Select comparison project:

Select the comparison project in this field. The comparison project is the original project to be compared to the incoming project. If the field does not contain a suitable comparison project, click (New) and select a project in the subsequent dialog.

Compare settings:

If the check box is selected, all project-related settings from the comparison and incoming projects - which you selected in the Scheme field in the comparison scheme for the operation - will be compared with each other.

Tip:

If you only want to compare the projects only with regard to the settings, the easiest way to do so is by using the search function within the settings: There simply enter the corresponding search term. This directly creates a type of filter, and the hierarchical tree structure is displayed for all the opened projects on the same tree structure.

Compare properties:

If the check box is selected, all properties from the comparison and incoming projects - which you selected in the Scheme field in the comparison scheme for the operation - will be compared with each other.

Perform project checks:

If the check box is selected, all project checks selected in the Scheme field in the check run scheme will be carried out during the project comparison as part of the project verification.

Compare project structures:

If the check box is selected, all project structures of the comparison and incoming projects will be compared during the project comparison operation of the project verification. All settings that you specified under Project > Properties in the Structure tab are compared.

Compare layers:

If the check box is selected, all layer settings of the comparison and incoming projects will be compared with each other during the project comparison operation of the project verification.

Stop comparison when first difference is found:

If the check box is selected, EPLAN interrupts all selected comparisons and check runs of the project verification as soon as a difference is found between relevant settings or properties of the comparison and incoming projects. The Project verification: Results dialog opens and EPLAN displays which actions can no longer be carried out.

See also