Updating Nailboards / Cable Drawings from Project Structure

Multiple nailboards / cable drawings can be updated from the project structure. You can select that either all nailboards / cable drawings are updated at once or just a selected one.

  1. To update all out-of-date nailboards / cable drawings at once, select the Nailboards / Cable drawings node from the Project structure tab.
  2. Click the (Update) button on the toolbar.

    All nailboards / cable drawings which are not up-to-date are updated.
  3. To update a selected nailboard / cable drawing, select an out-of-date nailboard / cable drawing from the Project structure tab.
  4. Click the (Update) button on the toolbar.

    The selected nailboard / cable drawing is updated.

Note:

The nailboard icon / cable drawing icon indicates an out-of-date state in the Project structure tab.

Note that if a document is closed and updated, it is also automatically saved and therefore the update cannot be undone. If a document is opened and updated from the Project structure tab, it must be saved by the user to keep the changes.